Year | Project | Customer | Services | Description |
1996 | Solids handling and dosing | ABB Umwelttechnik, Butzbach |
|
Technical consulting and support for limestone powder conveying and -injection into the absorber Melnik 1 (CR) |
1997 | Fluidized bed combustion systems | L. & C. Steinmüller, Gummersbach |
|
Conceptual design, calculation, design and basic engineering quotation for a power station (lignite coal, fluidized bed combustion) upgrade/uprate concerning coal handling, direct desulphurization and deashing, power station Javorzno (Poland) |
1997 | Pneumatic Ash conveying | L. & C. Steinmüller, Gummersbach |
|
Conceptual design, calculation, design and basic engineering quotation for a new power station (4x350 MWel) at Elbistan (Turkey), concerning fly and coarse ash handling as well as vapour ESP coal handling |
1997 | Solids handling and dosing | HKW Afferde |
|
Optimizing of dosing and injection of waste wood into a boiler with fluidised bed combustion, power station Afferde (Hameln, Germany) afterwards retrofitting of 5 lines with the same equipment |
1997 | Solids handling and dosing | Konsortium Steinmüller/Babcock/ VKR/Saarberg/Lurgi |
|
Engineering (calculation and design) for the coal dust handling for a pressurized coal dust combustion, Test installation Dorsten |
1997 | Fluidized bed combustion systems | L. & C. Steinmüller, Gummersbach |
|
start-up supervision of a 100 MWth fluidized bed power station at Tosa (Japan) |
1998 | Pneumatic Ash conveying | WSW Energie und Wasser AG (Wuppertaler Stadtwerke), HKW Wuppertal-Elberfeld |
|
Conceptual design, engineering, delivery and commissioning of a pneumatic conveying plant for hot deashing (max 500°C, 2 x 6 t/h) of the fluidized bed cooler of the fluidized bed boiler, power plant Elberfeld, Wuppertal (Germany) |
1999 | Pneumatic conveying of coal | L. & C. Steinmüller, Gummersbach |
|
study about different kinds of dosing and pneumatic conveying technics for using in a hard coal dust firing plant, power plant remounting Smijew (Ukraine) |
1999 | Flue gas cleaning | S.S.T. Schüttguttechnik GmbH, Landsberg/Lech |
|
study / measurement / consulting concerning additive conveyor system for flue gas cleaning KNT (Klausner-Nordic-Timper) in Wismar and Kirchmöser |
2000 | Dust collection | AE&E Austria |
|
Study and inspection of the separation process in a multicyclone vessel |
2001 | Anhydride conveying | Rocal Boxberg GmbH & Co.KG, Boxberg |
|
Inspection and measurement of the best possible condition for conveying hydrated AN, therefor optimising the system. |
2001 | Processed animal product | STEAG AG, Essen, Heizkraftwerk Herne |
|
Optimizing of plant; specifications and supply of a four way distributor (from DN 100 to 4xDN80)(manifold) for an animal processing direct firing system, also with by-pass air connection; optimisation of the processed animal incineration plant |
2001 | Pneumatic Ash conveying | RWE Power AG, KW Neurath |
|
Ash removal boiler in block D, Neurath power station. Engineering and installation to convert the existing conveying line. |
2002 | Processed animal product | WSW Energie und Wasser AG (Wuppertaler Stadtwerke), HKW Wuppertal-Elberfeld |
|
Engineering as well as component lay out ( silo, conveying componentry and various pipelines), instillation and commissioning of an animal processing plant conveying system with changeable componentry to a processed animal incineration plant. utilising: rotary airlock, injector, blower and a control valves. |
2003 | Pneumatic conveying | Simatek A/S, Dänemark |
|
Supply of DN 80 ejectors with ceramic diffusorsand non return valves, for the conveying of waste material from a waste incinerator |
2003 | Hydrated lime conveyance | W. Kurz & Söhne, Stahl- und Behälterbau, Brackenheim |
|
Supply of ejectors DN 50 and DN 80 with a special diffuser and components including drawings of injection nozzles and the delivery of a four way distributor (from DN 50 to 4xDN32). |
2004 | Hydrated lime conveyance | Gemeinschaftskraftwerk Schweinfurt GmbH (GKS), Schweinfurt |
|
Research for lime dosing and waste product transport |
2004 | Lime stone conveyance | Anlagenbau Flunkert, Bergheim |
|
Engineering for a conveying line, conveying fine lime stone (GKS Mannheim), delivery of ejectors, rotary blower and dosing unit. |
2004 | Pneumatic conveying of coal | RWE Power AG, Cost Center Fabrik, Service, Bergheim (Fabrik Fortuna Nord) |
|
Developement, technical process design, layout and construction details for a water jet pump for suction conveying, to be operated in a purging system for brown coal dust |
2005 | Pneumatic Ash conveying | EnBw AG, Stuttgart, RMHK Münster |
|
Consulting and documentation of a pressure conveyong vessel |
2006 | Pneumatic Ash conveying | RWE Power AG, KW Weisweiler |
|
Engineering for the combustion of additional material (layout of the conveying system for waste material and basic and detailed engineering of the conveying pipeline). |
2006 | Injection technology | Horsthemke GmbH, Beckum |
|
Pneumatic conveying of boiler ash "Project Rüdersdorf": Layout and basic engineering |
2006 | Brown coal dosing | Schwedes+Schulze Schüttguttechnik GmbH, Wolfenbüttel |
|
Process and technical layout for a pneumatic conveying pipeline |
2006 | Pneumatic conveying | Steinmüller Engineering GmbH, Gummersbach |
|
Basic engineering project (Tabor CZ) |
2006 | Pneumatic Ash conveying | Anlagenbau Flunkert, Bergheim |
|
Basic engineering and supply (pressure vessel conveyor) for the conveying of fly ash at GKM (powerstation in Mannheim) |
2007 | Pneumatic conveying | Steinmüller Engineering GmbH, Gummersbach |
|
Basic-Engineering for the project "ash-handling", Lünen and Mainz |
2007 | Pneumatic conveying | Steinmüller Engineering GmbH, Gummersbach |
|
Consulting and engineering for the project "tried brown coal", RWE |
2007 | Processed animal product | WSW Energie und Wasser AG (Wuppertaler Stadtwerke), HKW Wuppertal-Elberfeld |
|
Technical planing and preparation of licensing procedure for designing and operating of a co-combustion plant |
2008 | Pneumatic Ash conveying | EnBw AG, Stuttgart, RMHK Münster |
|
Basic-Engineering and optimazation of ash-handling plant |
2008 | Pneumatic Ash conveying | HEC GmbH, KW Bergkamen |
|
Pneumatic conveying of boiler ash and basic-engineering, calcualtion and bidders evaluation |
2008 | Pneumatic conveying of coal | RWE Power AG, KW Wachtberg |
|
Preliminary calculation and sizing of conveying pipes for wood chips. |
2009 | Pneumatic Ash conveying | CKD Praha Diz, TP Tabor, CZ |
|
Consulting on-site |
2009 | Coal, solids handling and dosing | Steinmüller Engineering GmbH, Gummersbach |
|
Basic-Engineering for safety storage and drying of lignite-coal (IHI-project) |
2009 | Hydrated lime conveyance | HELLMICH GmbH & Co. KG |
|
Basic-engineering and troubleshooting for flue gas treatment plan (HOK) and clciumhydroxide |
2010 | Pneumatic conveying | E.ON New Build & Technology GmbH, Gelsenkirchen |
|
Engineering: De-ashing Power Plant in Russia |
2011 | Coal, solids handling and dosing | Steinmüller Engineering GmbH, Gummersbach |
|
Engineering: Concept for co-combustion of biomass/Eskom, South-Africa |
2011 | Coal, solids handling and dosing | Fisia Babcok Environmental GmbH, Gummersbach |
|
Troubleshooting de-ashing E-Filter, Power Plant Neurath |
2012 | Solids handling and dosing | Heizkraftwerksgesellschaft Cottbus mbH, Cottbus |
|
Delivery of ejector DN80 |
2012 | Pneumatic Ash conveying | EnBw AG, Stuttgart, RMHK Münster |
|
Pneumatic ash removal for coal-fired boiler K25 in power plant Stgt.-Münster + tech.request for proposal |
2012 | Pressure vessel conveyor | Pressure vessel conveyor |
|
Feasibility study: Optimization of ash loading |
2012 | Pneumatic Ash conveying | Hamon Environmental GmbH, Köln |
|
expert opinion about pneumatic dust removal from an electric filter |
2013 | Hydrated lime conveyance | Schaub Umwelttechnik, Augsburg |
|
Assessment of pneumatic transport plant in Zorbau and delivery of ejector DN 100 |
2013 | Coal, solids handling and dosing | Steinmüller Engineering GmbH, Gummersbach |
|
Engineering fluized bed combustion |
2013 | Injection technology | Doosan Lentjes GmbH, Ratingen |
|
Delivery of splitter and hoses |
2013/2014 | Pneumatic Ash conveying | Hamon Environmental GmbH, Köln |
|
Engineering for instrumentation and valves for ESP, O-MON-Vietnam |
2014 | Cyclon | RWE PowerAG, Niederaußem |
|
Engineering Pre-Separator |
2014 | Pneumatic Ash conveying | (RWE Power AG) RV Handel und Dienstleistungen GmbH, Frechen |
|
Optimization of lime stone conveying |
2015 | Pneumatic Ash conveying | Andritz Energy & Environ-ment GmbH, Raaba, Austria | Examination of Lean phase conveying | |
2015 | Coal injection | AIR LIQUIDE Forschung und Entwicklung GmbH, Frankfurt |
|
Analysis of the solid-gas-circulation by pyrolysis of biomass |
2015 | Pneumatic Ash conveying | Hamon Research-Cottrell GmbH, Köln |
|
Expertise concerning filterdust quality |
2015 | Pneumatic Ash conveying | RWE Power AG, KW Neurath |
|
Supply of spare parts: Special diffusor (Al2O3) DN150 |
2016 |
Environmental engineering | IEM FörderTechnik GmbH,Kastl |
|
Analysis of activated carbon |
2016 | Coal injection | OERLIKON Schweißtechnik GmbH, Eisenberg |
|
Delivery of ejector DN80 and blower |
2016 | Pneumatic Ash conveying | Loibl (Allen Sherman-Hoff GmbH), Straubing |
|
Engineering Project Turow: Design of pneumatic conveying system |
2016 | Pneumatic conveying | Förder- und Anlagentechnik GmbH, Niederfischbach |
|
Calculation of pressure loss |
2016 | Coal injection | OERLIKON Schweißtechnik GmbH, Eisenberg |
|
Delivery of an ejector DN80 with ceramic diffuser |
2016 |
Fluidized bed combustion systems | L. & C. Steinmüller, Gummersbach |
|
Study: Waer in pneumatic conveying systems |
2017 | Pneumatic Ash conveying | Hamon Research-Cottrell GmbH, Werk Dobrawa |
|
Delivery of 4 6-way-splitter (dilute phase) |